A morning on a 96-metre housing plot: a groundworker, a steel fixer and a labourer cover 855 m over 27 legs between the gate, the laydown area, the mixer and block C, with the store-to-skip haul walked four times.

Template previewSpaghetti diagram
Plot 4 groundworks — week 6 site logisticsPlot 4855 m walked · 27 legs · 24 crossingsWelfare compoundMaterial laydownWork face — block CGate ×2Welfare ×5Store ×6Mixer ×3Rebar bay ×3Hoist ×3Block C L1 ×3Block C L2 ×2Skip ×325 mGroundworker — 368 m · 9 legsSteel fixer — 257 m · 9 legsLabourer — 230 m · 9 legsTotal travel855 mActors3Legs walked27Route crossings24Longest legBlock C L1 → Welfare · 60.…Most-travelled legSkip ↔ Store ×4Busiest stationStore ×6

Make it your own.

title "Plot 4 groundworks — week 6 site logistics"
scale 1m = 8px
room "Plot 4" 96m x 62m

zone "Welfare compound" at 4,4 size 16x12
zone "Material laydown" at 6,42 size 22x16
zone "Work face — block C" at 56,20 size 32x26

station Gate at 2,32
station Welfare at 12,10
station Store at 16,50
station Mixer at 34,44
station "Rebar bay" at 30,14
station Hoist at 58,34
station "Block C L1" at 70,26
station "Block C L2" at 78,40
station Skip at 44,56

path "Groundworker" : Welfare -> Store -> Mixer -> "Block C L1" -> Mixer -> "Block C L1" -> Skip -> Store -> "Block C L1" -> Welfare
path "Steel fixer" colour: red : Welfare -> "Rebar bay" -> Hoist -> "Block C L2" -> Hoist -> "Rebar bay" -> "Block C L2" -> Hoist -> "Rebar bay" -> Welfare
path "Labourer" colour: amber : Gate -> Store -> Skip -> Store -> Mixer -> Skip -> Store -> Gate -> Welfare -> Store