Risk Matrix — Offshore Wind Farm Construction and O&M Register

An owner's register for a fictional 1.2 GW offshore wind farm spanning grid, cables, installation, turbines and consents: controls cut exposure from 94 to 51 (−46%), and a delayed grid connection stays High 12 above the Medium appetite, with an interim 400 MW connection offer as the treatment. Illustrative register.

Template previewRisk matrix
Dogger North 1.2 GW offshore wind farm — construction and O&M risk registerOwner's register at final investment decision plus 12 monthsHEAT MAP · residual position, arrows from inherent11LOWLOW22LOWLOW33LOWLOW44LOWLOW55MEDIUMMEDIUM22LOWLOW44LOWLOW66MEDIUMMEDIUM88MEDIUMMEDIUM1010HIGHHIGH33LOWLOW66MEDIUMMEDIUM99MEDIUMMEDIUM1212HIGHHIGH1515HIGHHIGH44LOWLOW88MEDIUMMEDIUM1212HIGHHIGH1616VERY HIGHVERY HIGH2020VERY HIGHVERY HIGH55MEDIUMMEDIUM1010HIGHHIGH1515HIGHHIGH2020VERY HIGHVERY HIGH2525VERY HIGHVERY HIGHOW-07OW-06OW-03OW-05OW-08OW-02OW-08OW-07OW-04OW-01OW-03OW-06OW-01OW-02OW-05OW-04Rare<5%1Unlikely5–20%2Possible20–50%3Likely50–80%4Almost certain>80%51Insignificant<£0.5m2Minor£0.5–2m3Moderate£2–10m4Major£10–50m5Severe>£50m or fatalityLIKELIHOOD →IMPACT →R1residual position (after controls)R1inherent positioneffect of existing controlsappetite boundary · red ring = above it25L×I score and rating bandRISK PROFILE BY BANDInherentResidual (current)Very high0 → 0High6 → 1Medium2 → 5Low0 → 2Low 1–4 · Medium 5–9 · High 10–15 · Very high 16–25EXPOSURE Σ L×I51residual, after current controlsfrom 94 inherent · −46%HIGHEST RESIDUAL RISKOW-01Grid connection delayed by thetransmission operator12 · Highowner Grid Connection ManagerRISK APPETITEMedium or below1 risk above: OW-01Risk register8 risks · sorted by residual rating, then score#IDRISK, CONTROLS AND ACTIONSOWNERINHERENTRESIDUALTARGETCHANGEGRIDGrid connection delayed by the transmission operatorConnection agreement with delay compensationMonthly interface meetings with the transmission operator→Agree an interim connection offer for the first 400 MW — due 2027-09 ·Commercial Director1OW-01Grid ConnectionManager3 × 515 · High3 × 412 · HighABOVE APPETITE2 × 48 · Medium−3−20%↑ risingCABLESExport cable failure in the first five yearsBurial to 1.5 m depth from a cable burial risk assessmentCable protection systems at all third-party crossingsSpare export cable held in storage2OW-02Electrical PackageManager3 × 515 · High2 × 48 · Medium—−7−47%HEALTH & SAFETYCrew transfer injury stepping over from a crew transfer vesselMotion-compensated gangway used above 1.5 m significant wave heightGWO sea survival and transfer training for all technicians3OW-03HSE Manager3 × 412 · High2 × 36 · Medium—−6−50%TURBINESBlade leading-edge erosion earlier than designedLeading-edge protection shells fitted at the factoryAnnual drone inspection of every blade4OW-05Asset Manager4 × 312 · High2 × 36 · Medium—−6−50%FOUNDATIONSFatigue cracking in monopile secondary steelStructural health monitoring on twelve sentinel foundations5OW-08Asset Manager2 × 48 · Medium2 × 36 · Medium—−2−25%INSTALLATIONJack-up vessel weather downtime beyond the P50 allowanceInstallation programme planned on P90 weather windowsWeather-risk sharing in the vessel charter6OW-04Marine Coordinator4 × 312 · High3 × 26 · Medium—−6−50%SEABEDUnexploded ordnance found on the cable routeUXO survey with a target clearance campaignRoute micro-siting around confirmed targets7OW-06Marine PackageManager3 × 412 · High2 × 24 · Low—−8−67%CONSENTSMarine mammal noise limit breached during pilingSoft-start piling with double bubble curtainsMarine mammal observers and passive acoustic monitoring8OW-07EnvironmentalManager2 × 48 · Medium1 × 33 · Low—−5−63%FINDINGS8 risks rated — inherent 6 High, 2 Medium; after current controls 1 High, 5 Medium, 2 Low.Total exposure Σ(L×I) falls from 94 to 51 after current controls — a 46% reduction.Controls move 6 of 8 assessed risks into a lower band; 2 keep their inherent band.1 of 8 risks sits above the Medium appetite on residual rating — OW-01 (High 12); it has a treatment action.Highest residual risk: OW-01 Grid connection delayed by the transmission operator — High 12, owner Grid Connection Manager.Controls do most for OW-06: 12 → 4 (−67%).Illustrative register for a fictional project; costs and ratings are examples, not an assessment.

Make it your own.

title "Dogger North 1.2 GW offshore wind farm — construction and O&M risk register"
subtitle "Owner's register at final investment decision plus 12 months"
likelihood-levels: Rare (<5%), Unlikely (5–20%), Possible (20–50%), Likely (50–80%), Almost certain (>80%)
impact-levels: Insignificant (<£0.5m), Minor (£0.5–2m), Moderate (£2–10m), Major (£10–50m), Severe (>£50m or fatality)
bands: Low 1-4 green, Medium 5-9 yellow, High 10-15 orange, Very high 16-25 red
appetite: Medium
note "Illustrative register for a fictional project; costs and ratings are examples, not an assessment."

risk OW-01 "Grid connection delayed by the transmission operator"
  category: Grid
  owner: Grid Connection Manager
  likelihood: 3
  impact: 5
  control "Connection agreement with delay compensation"
  control "Monthly interface meetings with the transmission operator"
  residual: 3x4
  action "Agree an interim connection offer for the first 400 MW" due: 2027-09 owner: "Commercial Director"
  target: 2x4
  trend: rising

risk OW-02 "Export cable failure in the first five years"
  category: Cables
  owner: Electrical Package Manager
  likelihood: 3
  impact: 5
  control "Burial to 1.5 m depth from a cable burial risk assessment"
  control "Cable protection systems at all third-party crossings"
  control "Spare export cable held in storage"
  residual: 2x4

risk OW-03 "Crew transfer injury stepping over from a crew transfer vessel"
  category: Health & safety
  owner: HSE Manager
  likelihood: 3
  impact: 4
  control "Motion-compensated gangway used above 1.5 m significant wave height"
  control "GWO sea survival and transfer training for all technicians"
  residual: 2x3

risk OW-04 "Jack-up vessel weather downtime beyond the P50 allowance"
  category: Installation
  owner: Marine Coordinator
  likelihood: 4
  impact: 3
  control "Installation programme planned on P90 weather windows"
  control "Weather-risk sharing in the vessel charter"
  residual: 3x2

risk OW-05 "Blade leading-edge erosion earlier than designed"
  category: Turbines
  owner: Asset Manager
  likelihood: 4
  impact: 3
  control "Leading-edge protection shells fitted at the factory"
  control "Annual drone inspection of every blade"
  residual: 2x3

risk OW-06 "Unexploded ordnance found on the cable route"
  category: Seabed
  owner: Marine Package Manager
  likelihood: 3
  impact: 4
  control "UXO survey with a target clearance campaign"
  control "Route micro-siting around confirmed targets"
  residual: 2x2

risk OW-07 "Marine mammal noise limit breached during piling"
  category: Consents
  owner: Environmental Manager
  likelihood: 2
  impact: 4
  control "Soft-start piling with double bubble curtains"
  control "Marine mammal observers and passive acoustic monitoring"
  residual: 1x3

risk OW-08 "Fatigue cracking in monopile secondary steel"
  category: Foundations
  owner: Asset Manager
  likelihood: 2
  impact: 4
  control "Structural health monitoring on twelve sentinel foundations"
  residual: 2x3