Risk Matrix — Offshore Wind Farm Construction and O&M Register
An owner's register for a fictional 1.2 GW offshore wind farm spanning grid, cables, installation, turbines and consents: controls cut exposure from 94 to 51 (−46%), and a delayed grid connection stays High 12 above the Medium appetite, with an interim 400 MW connection offer as the treatment. Illustrative register.
Make it your own.
title "Dogger North 1.2 GW offshore wind farm — construction and O&M risk register"
subtitle "Owner's register at final investment decision plus 12 months"
likelihood-levels: Rare (<5%), Unlikely (5–20%), Possible (20–50%), Likely (50–80%), Almost certain (>80%)
impact-levels: Insignificant (<£0.5m), Minor (£0.5–2m), Moderate (£2–10m), Major (£10–50m), Severe (>£50m or fatality)
bands: Low 1-4 green, Medium 5-9 yellow, High 10-15 orange, Very high 16-25 red
appetite: Medium
note "Illustrative register for a fictional project; costs and ratings are examples, not an assessment."
risk OW-01 "Grid connection delayed by the transmission operator"
category: Grid
owner: Grid Connection Manager
likelihood: 3
impact: 5
control "Connection agreement with delay compensation"
control "Monthly interface meetings with the transmission operator"
residual: 3x4
action "Agree an interim connection offer for the first 400 MW" due: 2027-09 owner: "Commercial Director"
target: 2x4
trend: rising
risk OW-02 "Export cable failure in the first five years"
category: Cables
owner: Electrical Package Manager
likelihood: 3
impact: 5
control "Burial to 1.5 m depth from a cable burial risk assessment"
control "Cable protection systems at all third-party crossings"
control "Spare export cable held in storage"
residual: 2x4
risk OW-03 "Crew transfer injury stepping over from a crew transfer vessel"
category: Health & safety
owner: HSE Manager
likelihood: 3
impact: 4
control "Motion-compensated gangway used above 1.5 m significant wave height"
control "GWO sea survival and transfer training for all technicians"
residual: 2x3
risk OW-04 "Jack-up vessel weather downtime beyond the P50 allowance"
category: Installation
owner: Marine Coordinator
likelihood: 4
impact: 3
control "Installation programme planned on P90 weather windows"
control "Weather-risk sharing in the vessel charter"
residual: 3x2
risk OW-05 "Blade leading-edge erosion earlier than designed"
category: Turbines
owner: Asset Manager
likelihood: 4
impact: 3
control "Leading-edge protection shells fitted at the factory"
control "Annual drone inspection of every blade"
residual: 2x3
risk OW-06 "Unexploded ordnance found on the cable route"
category: Seabed
owner: Marine Package Manager
likelihood: 3
impact: 4
control "UXO survey with a target clearance campaign"
control "Route micro-siting around confirmed targets"
residual: 2x2
risk OW-07 "Marine mammal noise limit breached during piling"
category: Consents
owner: Environmental Manager
likelihood: 2
impact: 4
control "Soft-start piling with double bubble curtains"
control "Marine mammal observers and passive acoustic monitoring"
residual: 1x3
risk OW-08 "Fatigue cracking in monopile secondary steel"
category: Foundations
owner: Asset Manager
likelihood: 2
impact: 4
control "Structural health monitoring on twelve sentinel foundations"
residual: 2x3