Risk Matrix — High-Rise Construction Project Risk Register
A principal contractor's register for a fictional 18-storey residential tower, with impacts banded by cost and programme: controls bring exposure from 89 to 52 (−42%), and the two risks left above the Medium appetite are a delayed Building Safety Regulator Gateway 2 approval (High 12) and façade subcontractor insolvency (High 8), both with treatment actions. Illustrative register.
Make it your own.
title "Riverside Tower — 18-storey residential build, project risk register"
subtitle "Principal contractor's register at RIBA Stage 5 · higher-risk building under the Building Safety Act"
likelihood-levels: Rare (<5%), Unlikely (5–25%), Possible (25–50%), Likely (50–75%), Almost certain (>75%)
impact-levels: Insignificant (<£50k, <1 wk), Minor (£50–250k, 1–4 wks), Moderate (£250k–1m, 1–3 mths), Major (£1–3m, 3–6 mths), Severe (>£3m, >6 mths or fatality)
bands: Low 1-3, Medium 4-6, High 8-12, Critical 15-25
appetite: Medium
note "Illustrative register for a fictional development; costs, programme effects and ratings are examples, not an assessment."
risk C-01 "Gateway 2 approval from the Building Safety Regulator is delayed"
category: Regulatory
owner: Project Director
likelihood: 4
impact: 4
control "Pre-application engagement meetings with the regulator"
control "Principal designer appointed with a full golden-thread information plan"
residual: 3x4
action "Submit the Gateway 2 application 12 weeks ahead of programme" due: 2027-02 owner: "Design Manager"
target: 2x4
trend: stable
risk C-02 "Façade subcontractor becomes insolvent mid-package"
category: Commercial
owner: Commercial Manager
likelihood: 3
impact: 4
control "Parent company guarantee and a 10% performance bond"
control "Monthly subcontractor financial health checks"
residual: 2x4
action "Pre-qualify a reserve façade contractor" due: 2027-04 owner: "Procurement Lead"
risk C-03 "Unforeseen contamination found during piling"
category: Ground
owner: Project Manager
likelihood: 3
impact: 4
control "Phase 2 site investigation with 24 boreholes completed"
control "Contamination provisional sum of £400k in the budget"
residual: 2x3
risk C-04 "Dropped load or tower crane failure during lifting operations"
category: Health & safety
owner: Construction Manager
likelihood: 2
impact: 5
control "Lift plans by an appointed person to BS 7121"
control "Anemometer cut-off at 38 mph with daily wind briefings"
control "Six-monthly LOLER thorough examination"
residual: 1x5
risk C-05 "Fire in the partly completed building"
category: Health & safety
owner: Construction Manager
likelihood: 2
impact: 5
control "Fire safety plan to the Joint Code of Practice and HSG168"
control "Hot-works permits with a one-hour fire watch"
control "Temporary dry risers live from level 4"
residual: 1x5
risk C-06 "Structural steel prices rise before the frame order is placed"
category: Commercial
owner: Commercial Manager
likelihood: 4
impact: 3
control "60% of frame tonnage purchased early"
control "Fluctuation clause on the remaining steel package"
residual: 3x2
risk C-07 "Pre-commencement planning conditions are discharged late"
category: Regulatory
owner: Planning Consultant
likelihood: 3
impact: 3
control "Conditions tracker agreed with the local planning authority"
residual: 2x3
risk C-08 "Winter weather stops concrete pours"
category: Programme
owner: Project Manager
likelihood: 4
impact: 2
control "Winter working method statement with heated enclosures"
control "Accelerating admixtures approved by the structural engineer"
residual: 2x2