Roadmap — Net-Zero Transition Plan, 2026–2035

A ten-year climate transition roadmap for a fictional food manufacturer, one lane per emissions scope plus reporting, with the SBTi validation, the 2030 near-term target (Scope 1 and 2 down 42% on 2020, the 1.5 °C minimum) and 2035 net zero for Scope 1 and 2 as milestones: 13 items (3 done, 5 in progress, 4 planned, 1 at risk) and 3 milestones on a year axis, status date 30 Jun 2027. All 12 dependencies finish before their dependents start, and both targets wait for the work that delivers them. Illustrative roadmap.

Template previewRoadmap
Ashgrove Foods — net-zero transition roadmapAshgrove Foods — net-zero transition roadmapScope 1 and 2 −42% by 2030 against a 2020 base year, net zero by 2035 · Scope 3 through suppliers and packagingDone 3In progress 5Planned 4At risk 13 milestones12 dependenciesStatus date 30 Jun 2027LANES · YEAR2026202720282029203020312032203320342035MILESTONESToday · 30 Jun 2027Scope 1 — fleet andheat4 itemsScope 2 — electricity3 itemsScope 3 — suppliersand packaging3 items · 1 at riskReporting andassurance3 itemsISO 50001 energy audits, all sites · (2026) · doneHVO fuel for the HGV fleet · (2026 .. 2027) · in progress · 60%Steam boilers to heat pumps, 3 sites · (2027 .. 2029) · in progress · 15%Electric HGVs: 120 of 180 trucks · (2028 .. 2032) · plannedSolar PPA procurement, 45 GWh a year · (2026-03 .. 2026-12) · doneRooftop solar on 4 sites, 6 MWp · (2027 .. 2028) · in progress · 20%PPA supply: 60% of demand · (2028 .. 2035) · plannedTop 50 suppliers set science-based targets · (2026 .. 2028) · in progress · 40%Recyclable mono-material packaging · (2027 .. 2029) · at risk · owner Packaging leadRegenerative farming on 30% of wheat · (2029 .. 2033) · plannedClimate transition plan published · (2026-06 .. 2027-03) · doneAnnual GHG inventory, limited assurance · (2026 .. 2035) · in progress · 15%Reasonable assurance of Scope 1 and 2 · (2028 .. 2029) · plannedSBTi near-term targets validated · (2027-01-29) · milestone, achieved2030 target: Scope 1 and 2 −42% · (2030-12-31) · milestone, plannedScope 1 and 2 net zero · (2035-12-31) · milestone, plannedISO 50001 energy audits,all sitesHVO fuel for the HGV fleet · 60%Steam boilers to heat pumps, 3 sites · 15%Electric HGVs: 120 of 180 trucksSolar PPA procurement, 45 GWh a yearRooftop solar on 4 sites, 6 MWp · 20%PPA supply: 60% of demandTop 50 suppliers set science-based targets · 40%Recyclable mono-material packagingPackaging leadRegenerative farming on 30% of wheatClimate transitionplan publishedAnnual GHG inventory, limited assurance · 15%Reasonable assurance of Scope 1 and 2SBTi near-term targets validated2030 target: Scope 1 and 2 −42%Scope 1 and 2 net zeroCHECKS13 items in 4 lanes and 3 milestones: 3 done, 5 in progress, 4 planned, 1 at risk — every dependency finishes before its dependent starts.1 item at risk: “Recyclable mono-material packaging”.Longest dependency chain: “HVO fuel for the HGV fleet” → “Electric HGVs: 120 of 180 trucks” → “Scope 1 and 2 net zero” (3 steps, ending 31 Dec 2035).All 12 dependencies finish before their dependents start.Nothing is past its date and unfinished as of 30 Jun 2027.Illustrative example: Ashgrove Foods is fictional; targets, capacities and dates are invented for demonstration and are not a validated transition plan.

Make it your own.

title "Ashgrove Foods — net-zero transition roadmap"
subtitle "Scope 1 and 2 −42% by 2030 against a 2020 base year, net zero by 2035 · Scope 3 through suppliers and packaging"
note "Illustrative example: Ashgrove Foods is fictional; targets, capacities and dates are invented for demonstration and are not a validated transition plan."
axis years 2026 .. 2035
today 2027-06-30

milestone sbti "SBTi near-term targets validated" 2027-01-29 done after audits
milestone t2030 "2030 target: Scope 1 and 2 −42%" 2030-12-31 planned after heatpumps, rooftop, hvo
milestone nz2035 "Scope 1 and 2 net zero" 2035-12-31 planned after trucks, ppasupply

lane "Scope 1 — fleet and heat" color: orange
  item audits "ISO 50001 energy audits, all sites" 2026 done
  item hvo "HVO fuel for the HGV fleet" 2026 .. 2027 in progress 60%
  item heatpumps "Steam boilers to heat pumps, 3 sites" 2027 .. 2029 in progress 15% after audits
  item trucks "Electric HGVs: 120 of 180 trucks" 2028 .. 2032 planned after hvo

lane "Scope 2 — electricity" color: emerald
  item ppa "Solar PPA procurement, 45 GWh a year" 2026-03 .. 2026-12 done
  item rooftop "Rooftop solar on 4 sites, 6 MWp" 2027 .. 2028 in progress 20% after audits
  item ppasupply "PPA supply: 60% of demand" 2028 .. 2035 planned after ppa

lane "Scope 3 — suppliers and packaging" color: teal
  item suppliers "Top 50 suppliers set science-based targets" 2026 .. 2028 in progress 40%
  item packaging "Recyclable mono-material packaging" 2027 .. 2029 at risk owner: "Packaging lead"
  item regen "Regenerative farming on 30% of wheat" 2029 .. 2033 planned after suppliers

lane "Reporting and assurance" color: slate
  item plan "Climate transition plan published" 2026-06 .. 2027-03 done
  item inventory "Annual GHG inventory, limited assurance" 2026 .. 2035 in progress 15%
  item reasonable "Reasonable assurance of Scope 1 and 2" 2028 .. 2029 planned after plan