Feature Delivery (PERT)

Network from discovery to launch.

Template previewPERT / CPM network
New feature deliveryTotal duration: 35DiscoveryA · 5ES 0EF 5LS 0LF 5CRITICALDesignB · 8ES 5EF 13LS 5LF 13CRITICALBackendC · 12ES 13EF 25LS 13LF 25CRITICALFrontendD · 10ES 13EF 23LS 15LF 25slack 2IntegrationE · 4ES 25EF 29LS 25LF 29CRITICALQAF · 5ES 29EF 34LS 29LF 34CRITICALLaunchG · 1ES 34EF 35LS 34LF 35CRITICALShippedM

Make it your own.

title "New feature delivery"
task A "Discovery" duration 5
task B "Design" duration 8 after A
task C "Backend" duration 12 after B
task D "Frontend" duration 10 after B
task E "Integration" duration 4 after C,D
task F "QA" duration 5 after E
task G "Launch" duration 1 after F
milestone M "Shipped" after G