title "Planned substation outage - week 32"
column "Ready" wip 8
card "Isolate feeder 3 and apply earths" assignee "Cole" priority high tags "switching, permit"
card "Scaffold to the T2 bushings" assignee "Ade" tags "access"
card "Oil sample T1 and T2" assignee "Priya" priority medium tags "condition monitoring"
column "In progress" wip 4
card "Replace the T2 bushing set" assignee "Ade" priority urgent tags "long lead, critical path"
card "33 kV cable box refurbishment" assignee "Marek" priority high tags "critical path"
column "Blocked"
card "Relay firmware upgrade" assignee "Priya" priority high tags "vendor engineer delayed"
column "Testing"
card "Primary injection on feeder 3" assignee "Cole" priority high tags "commissioning"
column "Energised"
card "Bus coupler proving" assignee "Marek" tags "closed out"