Planned Substation Outage Board (Kanban)

A week-32 substation outage board with WIP limits, a blocked relay upgrade and the two critical-path tasks tagged.

Template previewKanban board
Planned substation outage - week 32Ready3 / 8Isolate feeder 3 and apply earthsCOColeswitchingpermitScaffold to the T2 bushingsADAdeaccessOil sample T1 and T2PRPriyacondition monitoringIn progress2 / 4Replace the T2 bushing setADAdelong leadcritical path33 kV cable box refurbishmentMAMarekcritical pathBlocked1Relay firmware upgradePRPriyavendor engineer delayedTesting1Primary injection on feeder 3COColecommissioningEnergised1Bus coupler provingMAMarekclosed out

Make it your own.

title "Planned substation outage - week 32"
column "Ready" wip 8
  card "Isolate feeder 3 and apply earths" assignee "Cole" priority high tags "switching, permit"
  card "Scaffold to the T2 bushings" assignee "Ade" tags "access"
  card "Oil sample T1 and T2" assignee "Priya" priority medium tags "condition monitoring"
column "In progress" wip 4
  card "Replace the T2 bushing set" assignee "Ade" priority urgent tags "long lead, critical path"
  card "33 kV cable box refurbishment" assignee "Marek" priority high tags "critical path"
column "Blocked"
  card "Relay firmware upgrade" assignee "Priya" priority high tags "vendor engineer delayed"
column "Testing"
  card "Primary injection on feeder 3" assignee "Cole" priority high tags "commissioning"
column "Energised"
  card "Bus coupler proving" assignee "Marek" tags "closed out"