EVM Performance Report — PV / EV / AC S-curve with CPI, SPI and EAC
Monthly earned value management report for a capital scheme: cumulative planned value, earned value and actual cost curves at the data date, with cost variance, schedule variance, CPI, SPI, TCPI and a CPI-based estimate at completion — the ANSI/EIA-748 figure a project controls manager files every period.
Make it your own.
title: Earned value at data date — Northgate WWTW Phase 2 membrane upgrade
subtitle: Cumulative £k, control account 3000. Data date: end of month 12 of 24.
x: Month after contract award
y: Cumulative cost (£k)
x limits: 0 .. 12
y limits: 0 .. 8000
grid: both
legend: right
line "PV — planned value (BCWS)" colour: blue curve: monotone
1 110
2 310
3 610
4 1020
5 1530
6 2120
7 2790
8 3510
9 4270
10 5060
11 5970
12 6900
line "EV — earned value (BCWP)" colour: green curve: monotone
1 105
2 295
3 570
4 940
5 1390
6 1900
7 2470
8 3080
9 3720
10 4410
11 5290
12 6210
line "AC — actual cost (ACWP)" colour: red curve: monotone
1 120
2 330
3 640
4 1050
5 1545
6 2110
7 2745
8 3420
9 4135
10 4900
11 5880
12 6900
note: BAC = £14,400k over 24 months. At the data date EV = £6,210k, so the scheme is 43.1% complete against a plan of 47.9%.
note: CV = EV − AC = 6,210 − 6,900 = −£690k. SV = EV − PV = 6,210 − 6,900 = −£690k.
note: CPI = EV/AC = 0.90. SPI = EV/PV = 0.90. Cumulative CPI has held between 0.90 and 0.91 since month 6, which is why it is used to project the EAC.
note: EAC = BAC/CPI = 14,400/0.90 = £16,000k. VAC = BAC − EAC = −£1,600k. TCPI(EAC) = (BAC−EV)/(EAC−AC) = 8,190/9,100 = 0.90.
note: The composite estimate EAC = AC + (BAC−EV)/(CPI×SPI) gives £17,011k. That is the figure carried in the risk case, not the reported EAC, and the two are not the same claim.
note: SV is in money, not time. It says £690k of planned work is undone; it does not say the finish date has moved. The finish date is a schedule question, answered by the network, not by this figure.