DSM — Offshore Wind Farm Delivery
Fourteen design and commissioning activities for a 1.2 GW offshore wind farm listed by contract package, computing that package order forces 14 rework loops against 3 in the partitioned sequence and isolating the four-way grid-connection loop (consent, export cable, onshore connection, offshore substation) and the vessel-schedule/installation-sequence pair.
Make it your own.
title "Offshore wind farm — design and commissioning"
mode process
convention ir-fad
# Listed by contract package — balance of plant, turbine supply, grid,
# marine, then the surveys everything else actually starts from.
activities: Foundation design, Array cable layout, Offshore substation, Export cable route
activities: Onshore connection, Turbine selection, Turbine commissioning, Grid compliance tests
activities: Consent conditions, Vessel schedule, Installation sequence, Handover to O&M
activities: Met-ocean survey, Geotechnical survey
Geotechnical survey <- Met-ocean survey
Turbine selection <- Met-ocean survey(3)
Foundation design <- Geotechnical survey(3), Turbine selection(3), Met-ocean survey(2)
Array cable layout <- Foundation design(2), Turbine selection(2)
Export cable route <- Onshore connection(3), Consent conditions(2)
Offshore substation <- Array cable layout(2), Export cable route(2), Onshore connection(2)
Onshore connection <- Consent conditions(2), Offshore substation(2)
Consent conditions <- Met-ocean survey(2), Export cable route(2)
Vessel schedule <- Foundation design(2), Installation sequence(3), Met-ocean survey(2)
Installation sequence <- Foundation design(2), Array cable layout(2), Offshore substation, Vessel schedule(3)
Turbine commissioning <- Installation sequence(3), Offshore substation(3), Turbine selection
Grid compliance tests <- Turbine commissioning(3), Onshore connection(3)
Handover to O&M <- Grid compliance tests(3), Turbine commissioning(2), Vessel schedule