All Four Dependencies — FS, SS, FF and SF, With Lead and Lag
Every precedence relationship in one plan, which Mermaid cannot express at all: finish-to-start, start-to-start, finish-to-finish and start-to-finish, each with a lag or a lead. `+10cd` is ten ELAPSED days — concrete does not stop curing on a Saturday — and the engine converts that to working days from wherever the predecessor actually lands. Reports clean.
Make it your own.
title "Ground floor slab"
start 2026-05-04
calendar mon-fri
section "Groundworks"
task dig "Excavate" 8d
task shore "Shoring" 5d after ss:dig +2d
task base "Blinding and formwork" 4d after dig
task pour "Pour slab" 2d after base
task cure "Cure" 10cd after pour
task strip "Strip formwork" 2d after cure
section "Following on"
task steel "Steel erection" 6d after strip
task survey "As-built survey" 3d after ff:steel
task night "Night watch handover" 4d after sf:steel
milestone slab "Slab complete" after survey