Teaching Case — A Start Date That Contradicts Its Own Plan
The defect this engine was built to catch, and it is invisible in every tool that draws what it is told. `cut` states it must start on 15 September; its own predecessors do not release it until the 29th — ten working days later. Both sentences are in the same document, both look entirely reasonable, and the drawing of the wrong one is identical to the drawing of the right one. The engine names the contradiction and counts the days.
Make it your own.
title "Magazine issue 47"
start 2026-09-01
calendar mon-fri
section "Editorial"
task brief "Commission" 3d
task write "Writing" 12d after brief
task edit "Sub-editing" 5d after write
task cut "Cut to length" 2d after edit start on 2026-09-15
section "Production"
task lay "Layout" 4d after cut
task proof "Proof" 3d after lay
milestone press "To press" after proof