Clinical Trial — Elapsed-Day Waiting Periods
Regulatory clocks do not pause for the weekend. Every waiting period here is written in calendar days (`30cd`), and the engine converts each one to working days from wherever its predecessor actually lands — so a submission that finishes on a Friday waits the same thirty days as one that finishes on a Tuesday, and the bars differ accordingly. Reports clean.
Make it your own.
title "Phase II — site activation"
start 2026-03-02
calendar mon-fri
deadline 2026-12-18 "First patient in"
section "Regulatory"
task proto "Protocol final" 15d
task ethics "Ethics submission" 5d after proto
task ewait "Ethics review clock" 60cd after ethics
task ca "Competent authority submission" 4d after proto
task cawait "Authority review clock" 45cd after ca
section "Sites"
task feas "Site feasibility" 20d after proto
task contr "Site contracts" 25d after feas
task init "Initiation visits" 12d after ewait, cawait, contr
section "Supply"
task label "Label and pack" 18d after proto
task ship "Ship to depots" 10cd after label
milestone fpi "First patient in" after init, ship