PERT — small construction
Single-family home critical-path plan.
Make it your own.
title "Single-family home build"
task A "Permits" duration 30
task B "Foundation" duration 14 after A
task C "Framing" duration 21 after B
task D "Roof" duration 7 after C
task E "Electrical" duration 14 after C
task F "Plumbing" duration 14 after C
task G "Drywall" duration 10 after D,E,F
task H "Finishes" duration 21 after G
task I "Inspection" duration 5 after H
milestone M "Move-in" after I