Roadmap — Five-Year Research Consortium by Work Package

A five-year consortium grant on peatland restoration laid out by work package on a year axis, with deliverables and the funder's review points as milestones: 16 items (4 done, 4 in progress, 7 planned, 1 at risk) and 4 milestones in six lanes, status date 20 Sep 2027. All 20 dependencies finish before their dependents start; the longest chain, seven steps, runs from the kick-off through site instrumentation, the v1 carbon model, the mid-term review and the policy briefs to the final synthesis and the programme end. Illustrative roadmap.

Template previewRoadmap
PEATFLUX — consortium research roadmap 2026–2030PEATFLUX — consortium research roadmap 2026–2030Six work packages · deliverables (D) and milestones (MS) as numbered in the grant agreementDone 4In progress 4Planned 7At risk 14 milestones20 dependenciesStatus date 20 Sep 2027LANES · YEAR20262027202820292030MILESTONESToday · 20 Sep 2027WP1 Management andethics2 itemsWP2 Field monitoring3 itemsWP3 Processmodelling3 itemsWP4 Remote sensingand data3 items · 1 milestone1 at riskWP5 Policy andstakeholders2 itemsWP6 Synthesis anddissemination3 itemsKick-off and consortium agreement · (2026-01 .. 2026-03) · doneD1.2 Data management plan (FAIR) · (2026-04 .. 2026-06) · doneInstrument 12 peatland sites · (2026-04 .. 2026-12) · done · owner Field teamMonitoring years 1–2 (eddy covariance) · (2027-01 .. 2028-12) · in progress · 35%Monitoring years 3–4 · (2029-01 .. 2030-06) · plannedPeat carbon model v1 calibrated · (2027-01 .. 2027-12) · in progress · 60%Model v2 with restoration scenarios · (2028-01 .. 2029-06) · planned2050 emission projections by scenario · (2029-07 .. 2030-09) · plannedWater-table retrieval from Sentinel-1 · (2026-07 .. 2027-12) · in progress · 70%Open data cube v1 · (2027-06 .. 2028-03) · at risk · owner Data stewardD4.3 Open data release · (2028-06-30) · milestone, plannedData cube v2 with model outputs · (2029-07 .. 2030-06) · plannedStakeholder panel: three national workshops · (2026-09 .. 2027-06) · donePolicy briefs for national peatland strategies · (2029-01 .. 2030-06) · plannedPeer-reviewed papers and open-access preprints · (2027-06 .. 2030-12) · in progress · 15%Summer school for early-career researchers · (2028-07 .. 2028-09) · plannedFinal synthesis report · (2030-10 .. 2030-12) · plannedGrant start · (2026-01-01) · milestone, achievedMS3 Mid-term review with the funder · (2028-06-30) · milestone, plannedProgramme end · (2030-12-31) · milestone, plannedKick-off and consortium agreementD1.2 Data management plan (FAIR)Instrument 12peatland sitesField teamMonitoring years 1–2 (eddy covariance) · 35%Monitoring years 3–4Peat carbon model v1calibrated · 60%Model v2 with restoration scenarios2050 emission projections byscenarioWater-table retrieval fromSentinel-1 · 70%Open data cube v1Data stewardD4.3 Open data releaseData cube v2 with modeloutputsStakeholder panel: three national workshopsPolicy briefs for national peatlandstrategiesPeer-reviewed papers and open-access preprints · 15%Summer school for early-career researchersFinal synthesis reportGrant startMS3 Mid-term review with the funderProgramme endCHECKS16 items in 6 lanes and 4 milestones: 4 done, 4 in progress, 7 planned, 1 at risk — every dependency finishes before its dependent starts.1 item at risk: “Open data cube v1”.Longest dependency chain: “Kick-off and consortium agreement” → “Instrument 12 peatland sites” → “Peat carbon model v1 calibrated” → “MS3 Mid-term review with the funder” → “Policy briefs for nationalpeatland strategies” → “Final synthesis report” → “Programme end” (7 steps, ending 31 Dec 2030).All 20 dependencies finish before their dependents start.Nothing is past its date and unfinished as of 20 Sep 2027.Illustrative example: PEATFLUX is a fictional consortium; sites, deliverables and dates are invented for demonstration.

Make it your own.

title "PEATFLUX — consortium research roadmap 2026–2030"
subtitle "Six work packages · deliverables (D) and milestones (MS) as numbered in the grant agreement"
note "Illustrative example: PEATFLUX is a fictional consortium; sites, deliverables and dates are invented for demonstration."
axis years 2026 .. 2030
today 2027-09-20

milestone start "Grant start" 2026-01-01 done
milestone midterm "MS3 Mid-term review with the funder" 2028-06-30 planned after model1, panel
milestone end "Programme end" 2030-12-31 planned after final

lane "WP1 Management and ethics" color: slate
  item kickoff "Kick-off and consortium agreement" 2026-01 .. 2026-03 done
  item dmp "D1.2 Data management plan (FAIR)" 2026-04 .. 2026-06 done after kickoff

lane "WP2 Field monitoring" color: emerald
  item sites "Instrument 12 peatland sites" 2026-04 .. 2026-12 done after kickoff owner: "Field team"
  item campaign1 "Monitoring years 1–2 (eddy covariance)" 2027-01 .. 2028-12 in progress 35% after sites
  item campaign2 "Monitoring years 3–4" 2029-01 .. 2030-06 planned after campaign1

lane "WP3 Process modelling" color: violet
  item model1 "Peat carbon model v1 calibrated" 2027-01 .. 2027-12 in progress 60% after sites
  item model2 "Model v2 with restoration scenarios" 2028-01 .. 2029-06 planned after model1
  item proj "2050 emission projections by scenario" 2029-07 .. 2030-09 planned after model2

lane "WP4 Remote sensing and data" color: sky
  item sar "Water-table retrieval from Sentinel-1" 2026-07 .. 2027-12 in progress 70%
  item cube "Open data cube v1" 2027-06 .. 2028-03 at risk after dmp owner: "Data steward"
  milestone release "D4.3 Open data release" 2028-06-30 planned after cube, sar
  item cube2 "Data cube v2 with model outputs" 2029-07 .. 2030-06 planned after release, model2

lane "WP5 Policy and stakeholders" color: amber
  item panel "Stakeholder panel: three national workshops" 2026-09 .. 2027-06 done
  item briefs "Policy briefs for national peatland strategies" 2029-01 .. 2030-06 planned after midterm

lane "WP6 Synthesis and dissemination" color: rose
  item papers "Peer-reviewed papers and open-access preprints" 2027-06 .. 2030-12 in progress 15%
  item school "Summer school for early-career researchers" 2028-07 .. 2028-09 planned after midterm
  item final "Final synthesis report" 2030-10 .. 2030-12 planned after proj, campaign2, briefs