Roadmap — Hardware Product Through EVT, DVT and PVT Gates
A stage-gated hardware roadmap for a fictional 22 kW wall-box EV charger, from engineering validation to mass production, with gate reviews as milestones on the band above the lanes: 16 items (3 done, 5 in progress, 7 planned, 1 at risk) and 4 milestones over six quarters, status date 10 Jun 2027. All 22 dependencies finish before their dependents start, including CE (LVD, EMC, RED) and UL 2594 testing after design validation, and the longest chain runs from the G2 concept freeze through EVT, DVT and the CE campaign to the retail launch. Illustrative roadmap.
Make it your own.
title "Voltaris W22 wall-box charger — programme roadmap"
subtitle "Engineering, certification and supply chain to production release · gate reviews on the top band"
note "Illustrative example: Voltaris is a fictional manufacturer; quantities, test plans and dates are invented and are not compliance advice."
axis quarters 2027-Q1 .. 2028-Q2
today 2027-06-10
milestone g2 "G2 Concept freeze" 2027-01-29 done
milestone g3 "G3 Design freeze" 2027-09-30 planned after dvt
milestone g4 "G4 Production release" 2028-01-31 planned after pvt, ce
milestone launch "Retail launch" 2028-03-15 planned after g4, ul
lane "Electrical hardware" color: orange
item evt "EVT: power board and metering rev A" 2027-02 .. 2027-04 done after g2
item dvt "DVT: rev B boards, 60 units" 2027-05 .. 2027-09 in progress 30% after evt
item pvt "PVT: pilot build on the production line" 2027-11 .. 2028-01 planned after dvt, tooling
lane "Mechanical and thermal" color: slate
item enclosure "Enclosure design to IK10 and IP65" 2027-02 .. 2027-04 done after g2
item tooling "Injection-mould tooling, T1 to T3" 2027-05 .. 2027-10 in progress 20% after enclosure
item thermal "Thermal derating tests at 50 °C" 2027-08 .. 2027-09 planned after enclosure
lane "Firmware and cloud" color: violet
item ocpp "OCPP 2.0.1 charge-point stack" 2027-01 .. 2027-06 in progress 85%
item pnc "ISO 15118 Plug & Charge" 2027-07 .. 2027-12 planned after ocpp
item ota "Signed over-the-air updates" 2027-04 .. 2027-08 at risk owner: "Firmware security"
lane "Certification" color: rose
item precompliance "EMC pre-compliance scans" 2027-06 .. 2027-08 in progress 10% after evt
item ce "CE test campaign: LVD, EMC and RED" 2027-10 .. 2027-12 planned after dvt, precompliance
item ul "UL 2594 and UL 2231 listing" 2027-10 .. 2028-02 planned after dvt owner: "Compliance lead"
lane "Manufacturing and supply" color: teal
item cm "Contract manufacturer selected" 2027-03 .. 2027-05 done
item longlead "Long-lead buy: relays, RCD modules, MCUs" 2027-06 .. 2027-08 in progress 15% after cm
item eol "End-of-line test station" 2027-09 .. 2027-11 planned after longlead
item ramp "Ramp to 2,000 units a month" 2028-02 .. 2028-06 planned after pvt, ce, eol