Asset commissioning and defect closure

Preserves hold points and distinguishes physical installation from operational acceptance. Original worked design example; adapt responsibilities, thresholds and assumptions to your system.

Template previewMermaid
Rendering…

What this template contains

Diagram type
State diagram
Source
14 lines

Make it your own.

stateDiagram-v2
[*] --> Installed
Installed --> Prechecks: verify completion dossier
Prechecks --> DefectOpen: missing or failed check
DefectOpen --> Repair: assign corrective action
Repair --> Prechecks: evidence resubmitted
Prechecks --> EnergizationApproved: prerequisites accepted
EnergizationApproved --> FunctionalTest: controlled activation
FunctionalTest --> DefectOpen: performance failure
FunctionalTest --> TrialOperation: acceptance criteria met
TrialOperation --> FunctionalTest: instability detected
TrialOperation --> Handover: stable duty demonstrated
Handover --> Operational: owner accepts records
Operational --> [*]