PERT / CPM network templates

Software Release (PERT)

Task network from code freeze to production.

Template previewPERT / CPM network
Software releaseTotal duration: 14Code freezeA · 1ES 0EF 1LS 0LF 1CRITICALRegression testsB · 5ES 1EF 6LS 1LF 6CRITICALBug fixesC · 4ES 6EF 10LS 6LF 10CRITICALRelease notesD · 2ES 1EF 3LS 9LF 11slack 8Staging deployE · 1ES 10EF 11LS 10LF 11CRITICALSign-offF · 2ES 11EF 13LS 11LF 13CRITICALProduction deployG · 1ES 13EF 14LS 13LF 14CRITICALReleasedM

Make it your own.

title "Software release"
task A "Code freeze" duration 1
task B "Regression tests" duration 5 after A
task C "Bug fixes" duration 4 after B
task D "Release notes" duration 2 after A
task E "Staging deploy" duration 1 after C
task F "Sign-off" duration 2 after E,D
task G "Production deploy" duration 1 after F
milestone M "Released" after G