Refinery Turnaround Schedule (Crude Unit)

A 24-day crude unit shutdown from feed cut to feed-in, with inspection findings driving the repair scope.

Template previewMermaid
Rendering…

Make it your own.

gantt
    title Crude unit turnaround - 24 day window
    dateFormat YYYY-MM-DD
    axisFormat %d %b
    section Shutdown
    Feed cut and controlled cool down    :done, sd1, 2026-03-02, 2d
    Steam out, blind list and gas free   :done, sd2, after sd1, 2d
    section Inspection
    Vessel entry and NDT on C-101        :active, in1, after sd2, 4d
    Furnace tube IRIS survey             :in2, after sd2, 3d
    section Repairs
    Tray replacement C-101 trays 12-28   :rp1, after in1, 5d
    Furnace tube renewal - 14 tubes      :rp2, after in2, 6d
    Exchanger bundle cleaning E-201/202  :rp3, after sd2, 7d
    Relief valve overhaul and test       :rp4, after sd2, 5d
    section Restart
    Box up and leak test                 :rs1, after rp1 rp2 rp3 rp4, 2d
    Dry out and tightness test           :rs2, after rs1, 1d
    Feed in                              :milestone, m1, after rs2, 0d