A skilled-person redress programme whose 128-working-day critical path runs through methodology agreement rather than the data extract.

Template previewPERT / CPM network
Customer redress remediation (working days)Total duration: 128 daysScope the affected populationA · 15dES 0EF 15LS 0LF 15CRITICALData extract and reconciliationB · 20dES 15EF 35LS 20LF 40slack 5Agree the redress methodologyC · 25dES 15EF 40LS 15LF 40CRITICALBuild the calculation engineD · 30dES 40EF 70LS 40LF 70CRITICALIndependent calculation assuranceE · 12dES 70EF 82LS 70LF 82CRITICALCustomer contact strategy and lettersF · 18dES 40EF 58LS 64LF 82slack 24Pilot 500 casesG · 10dES 82EF 92LS 82LF 92CRITICALFull run and payment fileH · 22dES 92EF 114LS 92LF 114CRITICALSkilled person attestationI · 14dES 114EF 128LS 114LF 128CRITICALClose the requirement noticeM

Make it your own.

title "Customer redress remediation (working days)"
unit days
task A "Scope the affected population" duration 15
task B "Data extract and reconciliation" duration 20 after A
task C "Agree the redress methodology" duration 25 after A
task D "Build the calculation engine" duration 30 after B,C
task E "Independent calculation assurance" duration 12 after D
task F "Customer contact strategy and letters" duration 18 after C
task G "Pilot 500 cases" duration 10 after E,F
task H "Full run and payment file" duration 22 after G
task I "Skilled person attestation" duration 14 after H
milestone M "Close the requirement notice" after I