PERT / CPM network templates

PERT — mobile app release

Eight-week iOS/Android release with staged rollout.

Template previewPERT / CPM network
Mobile releaseTotal duration: 28SpecA · 4ES 0EF 4LS 0LF 4CRITICALCore buildB · 12ES 4EF 16LS 4LF 16CRITICALPush & authC · 4ES 4EF 8LS 12LF 16slack 8AnalyticsD · 3ES 16EF 19LS 22LF 25slack 6BetaE · 5ES 16EF 21LS 16LF 21CRITICALStore reviewF · 4ES 21EF 25LS 21LF 25CRITICALStaged rolloutG · 3ES 25EF 28LS 25LF 28CRITICAL100 % liveM

Make it your own.

title "Mobile release"
task A "Spec"            duration 4
task B "Core build"      duration 12 after A
task C "Push & auth"     duration 4  after A
task D "Analytics"       duration 3  after B
task E "Beta"            duration 5  after B,C
task F "Store review"    duration 4  after E
task G "Staged rollout"  duration 3  after F,D
milestone M "100 % live" after G