Assembly Line Relocation (PERT)
Moving assembly line 2 to a new bay in 49 days, where civils and services rather than the conveyor lead time drive the critical path.
Make it your own.
title "Relocating assembly line 2 to the new bay (days)"
unit days
task A "Freeze the layout and services drawings" duration 5
task B "Order and receive the conveyor sections" duration 25 after A
task C "Civils - trench, pit and floor levelling" duration 12 after A
task D "Compressed air and three-phase drops" duration 8 after C
task E "Decommission and clean the old line" duration 4 after A
task F "Move and set the machines" duration 6 after D,E
task G "Install and align the conveyor" duration 7 after B,F
task H "Safety validation and conformity review" duration 5 after G
task I "Dry cycle and run at rate" duration 6 after H
task J "Train both shifts to the new standard work" duration 4 after H
milestone M "Full rate production" after I,J