Assembly Line Relocation (PERT)

Moving assembly line 2 to a new bay in 49 days, where civils and services rather than the conveyor lead time drive the critical path.

Template previewPERT / CPM network
Relocating assembly line 2 to the new bay (days)Total duration: 49 daysFreeze the layout and services drawingsA · 5dES 0EF 5LS 0LF 5CRITICALOrder and receive the conveyor sectionsB · 25dES 5EF 30LS 6LF 31slack 1Civils - trench, pit and floor levellingC · 12dES 5EF 17LS 5LF 17CRITICALCompressed air and three-phase dropsD · 8dES 17EF 25LS 17LF 25CRITICALDecommission and clean the old lineE · 4dES 5EF 9LS 21LF 25slack 16Move and set the machinesF · 6dES 25EF 31LS 25LF 31CRITICALInstall and align the conveyorG · 7dES 31EF 38LS 31LF 38CRITICALSafety validation and conformity reviewH · 5dES 38EF 43LS 38LF 43CRITICALDry cycle and run at rateI · 6dES 43EF 49LS 43LF 49CRITICALTrain both shifts to the new standard workJ · 4dES 43EF 47LS 45LF 49slack 2Full rate productionM

Make it your own.

title "Relocating assembly line 2 to the new bay (days)"
unit days
task A "Freeze the layout and services drawings" duration 5
task B "Order and receive the conveyor sections" duration 25 after A
task C "Civils - trench, pit and floor levelling" duration 12 after A
task D "Compressed air and three-phase drops" duration 8 after C
task E "Decommission and clean the old line" duration 4 after A
task F "Move and set the machines" duration 6 after D,E
task G "Install and align the conveyor" duration 7 after B,F
task H "Safety validation and conformity review" duration 5 after G
task I "Dry cycle and run at rate" duration 6 after H
task J "Train both shifts to the new standard work" duration 4 after H
milestone M "Full rate production" after I,J