CFD — Software Delivery Team
Ten weeks of a platform team's Kanban board, computing WIP from the commitment point, weekly throughput, Little's Law cycle time and the flow efficiency lost to the review queue.
Make it your own.
title "Platform team — Q3 delivery flow"
unit stories
stages: Backlog*, Ready*, In progress, Review*, Done
commit Ready
wip-limit "In progress" 8
# Cumulative stories that have ENTERED each stage by that Monday.
2024-07-01 | 148, 26, 8, 4, 0
2024-07-08 | 156, 34, 18, 13, 9
2024-07-15 | 165, 44, 29, 23, 19
2024-07-22 | 173, 55, 40, 33, 28
2024-07-29 | 182, 66, 51, 43, 38
2024-08-05 | 192, 78, 62, 53, 47
2024-08-12 | 203, 90, 75, 65, 58
2024-08-19 | 214, 103, 88, 78, 70
2024-08-26 | 226, 117, 102, 92, 83
2024-09-02 | 239, 131, 116, 106, 96