Project Management — quarterly roadmap
Project-management vertical — a quarterly roadmap, drawn by gantt. Typed FlowScript for project management. Keywords: Gantt, roadmap, milestone, sprint, timeline.
Make it your own.
// Project-management vertical — a quarterly roadmap, drawn by gantt.
//
// Project, milestone and task blocks. The dependency edges are declared
// rather than inferred — depends: [x] is what puts an arrow on the
// timeline — so a task that slips and a task that merely happens to
// start late are different statements in the figure.
project q3_launch {
title: "Q3 product launch"
start: "2026-07-01"
end: "2026-09-30"
owner: "Lina Park"
}
milestone beta_open {
date: "2026-07-22"
title: "Open beta to first 500 design partners"
status: "planned"
}
milestone ga {
date: "2026-09-15"
title: "General availability"
status: "planned"
}
task auth_overhaul {
title: "Migrate auth to passkeys + WebAuthn"
start: "2026-07-01"
end: "2026-07-28"
assignee: "Auth team"
}
task billing {
title: "Stripe integration + invoicing"
start: "2026-07-15"
end: "2026-08-10"
depends: [auth_overhaul]
assignee: "Platform"
}
task docs {
title: "Public docs site + API reference"
start: "2026-08-01"
end: "2026-09-05"
depends: [billing]
assignee: "DevRel"
}
view timeline: gantt(q3_launch)