PERT / CPM network templates

PERT — warehouse relocation

Critical path for shutting down old DC and standing up the new one without downtime.

Template previewPERT / CPM network
Warehouse moveTotal duration: 121Lease & permitsA · 30ES 0EF 30LS 0LF 30CRITICALBuild-outB · 60ES 30EF 90LS 30LF 90CRITICALRacks & dockC · 21ES 90EF 111LS 90LF 111CRITICALWMS setupD · 28ES 30EF 58LS 83LF 111slack 53Hire local staffE · 21ES 30EF 51LS 90LF 111slack 60Inventory auditF · 14ES 30EF 44LS 97LF 111slack 67Pilot runG · 7ES 111EF 118LS 111LF 118CRITICALCutoverH · 3ES 118EF 121LS 118LF 121CRITICALLiveM

Make it your own.

title "Warehouse move"
task A "Lease & permits"   duration 30
task B "Build-out"         duration 60 after A
task C "Racks & dock"      duration 21 after B
task D "WMS setup"         duration 28 after A
task E "Hire local staff"  duration 21 after A
task F "Inventory audit"   duration 14 after A
task G "Pilot run"         duration 7  after C,D,E,F
task H "Cutover"           duration 3  after G
milestone M "Live"         after H