PERT / CPM network templates

Conference Planning (PERT)

Task network for organising a conference.

Template previewPERT / CPM network
Conference planningTotal duration: 30Set date and venueA · 5ES 0EF 5LS 0LF 5CRITICALOpen registrationB · 3ES 5EF 8LS 5LF 8CRITICALInvite speakersC · 10ES 5EF 15LS 13LF 23slack 8MarketingD · 20ES 8EF 28LS 8LF 28CRITICALFinalise agendaE · 5ES 15EF 20LS 23LF 28slack 8LogisticsF · 8ES 5EF 13LS 20LF 28slack 15Run eventG · 2ES 28EF 30LS 28LF 30CRITICALEvent dayM

Make it your own.

title "Conference planning"
task A "Set date and venue" duration 5
task B "Open registration" duration 3 after A
task C "Invite speakers" duration 10 after A
task D "Marketing" duration 20 after B
task E "Finalise agenda" duration 5 after C
task F "Logistics" duration 8 after A
task G "Run event" duration 2 after D,E,F
milestone M "Event day" after G