PERT / CPM network templates

PERT — research conference

Critical-path plan for a four-day academic conference.

Template previewPERT / CPM network
Academic conferenceTotal duration: 60Theme & CFPA · 7ES 0EF 7LS 0LF 7CRITICALReviewersB · 14ES 7EF 21LS 14LF 28slack 7ReviewsC · 21ES 21EF 42LS 28LF 49slack 7ProgramD · 7ES 42EF 49LS 49LF 56slack 7Venue bookingE · 14ES 7EF 21LS 21LF 35slack 14SponsorshipsF · 28ES 7EF 35LS 7LF 35CRITICALLogisticsG · 21ES 35EF 56LS 35LF 56CRITICALMarketingH · 30ES 7EF 37LS 26LF 56slack 19Run conferenceI · 4ES 56EF 60LS 56LF 60CRITICALWrapM

Make it your own.

title "Academic conference"
task A "Theme & CFP"        duration 7
task B "Reviewers"          duration 14 after A
task C "Reviews"            duration 21 after B
task D "Program"            duration 7  after C
task E "Venue booking"      duration 14 after A
task F "Sponsorships"       duration 28 after A
task G "Logistics"          duration 21 after E,F
task H "Marketing"          duration 30 after A
task I "Run conference"     duration 4  after D,G,H
milestone M "Wrap"          after I