PERT / CPM network templates

PERT — consumer hardware

EVT / DVT / PVT path with critical certification stage.

Template previewPERT / CPM network
Consumer hardware launchTotal duration: 172Industrial designA · 30ES 0EF 30LS 0LF 30CRITICALID lockB · 5ES 30EF 35LS 30LF 35CRITICALElectrical EVTC · 25ES 35EF 60LS 35LF 60CRITICALMechanical EVTD · 20ES 35EF 55LS 40LF 60slack 5EVT buildE · 14ES 60EF 74LS 60LF 74CRITICALDVTF · 21ES 74EF 95LS 74LF 95CRITICALCertificationG · 28ES 95EF 123LS 95LF 123CRITICALPVTH · 14ES 123EF 137LS 123LF 137CRITICALMass productionI · 35ES 137EF 172LS 137LF 172CRITICALShipM

Make it your own.

title "Consumer hardware launch"
task A "Industrial design"  duration 30
task B "ID lock"            duration 5  after A
task C "Electrical EVT"     duration 25 after B
task D "Mechanical EVT"     duration 20 after B
task E "EVT build"          duration 14 after C,D
task F "DVT"                duration 21 after E
task G "Certification"      duration 28 after F
task H "PVT"                duration 14 after G
task I "Mass production"    duration 35 after H
milestone M "Ship"          after I