House Build (PERT)

Critical-path network for building a house.

Template previewPERT / CPM network
House buildTotal duration: 53FoundationA · 10ES 0EF 10LS 0LF 10CRITICALFramingB · 14ES 10EF 24LS 10LF 24CRITICALRoofingC · 7ES 24EF 31LS 24LF 31CRITICALPlumbingD · 6ES 24EF 30LS 25LF 31slack 1ElectricalE · 6ES 24EF 30LS 25LF 31slack 1InsulationF · 4ES 31EF 35LS 31LF 35CRITICALDrywallG · 8ES 35EF 43LS 35LF 43CRITICALFinishingH · 10ES 43EF 53LS 43LF 53CRITICALHandoverM

Make it your own.

title "House build"
task A "Foundation" duration 10
task B "Framing" duration 14 after A
task C "Roofing" duration 7 after B
task D "Plumbing" duration 6 after B
task E "Electrical" duration 6 after B
task F "Insulation" duration 4 after C,D,E
task G "Drywall" duration 8 after F
task H "Finishing" duration 10 after G
milestone M "Handover" after H