Decision Matrix — Distribution Centre Site Selection
Four distribution-centre sites compared on modelled drive time, lease cost, labour pool and grid capacity, plus scored flood, expansion and planning risk on a 1–10 scale. Site C's 3.2 MVA supply fails the 4 MVA must-have; Site A ranks first at 7.22 of 10, 0.67 ahead of Site D, and stays ahead unless the weight on lease cost rises from 20% to 25.6%. Illustrative values.
Make it your own.
title "Northern distribution centre — site selection"
subtitle "Four shortlisted sites, measured where possible and scored 1–10 where not"
scale 1-10
note "Illustrative data for a fictional grocery retailer; drive times are modelled to its 142 stores."
options "Site A · motorway park" | "Site B · port-side" | "Site C · greenfield" | "Site D · brownfield retrofit"
"Mean drive time to stores" weight 25 unit "min" lower : 74 96 81 88
"Lease and business rates" weight 20 unit "£k/yr" lower : 2,340 1,860 2,050 1,520
"Labour pool within 30 minutes" weight 15 unit "k people" : 410 265 190 335
"Grid power available" weight 10 unit "MVA" must >= 4 : 6.5 8 3.2 5
"Flood risk (1 = negligible)" weight 10 lower : 2 6 1 3
"Room to expand" weight 10 : 6 4 9 3
"Planning risk (1 = low)" weight 10 lower : 3 5 7 2