Decision Tree — Tender Strategy: Bid High, Bid Low or Walk Away
A contractor's bid decision with a downstream procurement choice: bidding high wins less often but rolls back to $447k against $264k for bidding low, and in both branches a fixed-price steelwork subcontract beats self-performing once overrun risk is priced in. Illustrative values.
Make it your own.
title "Hospital wing tender — bid high, bid low or walk away?"
subtitle "Expected contractor profit, US$ thousands, after a US$120k bid-preparation cost"
currency $
unit k
risk-profile compare
terminals natural
note "Win rates from the last 24 comparable tenders; overrun bands from the firm's cost-report history."
note "Illustrative values for a fictional contractor."
decision "Tender strategy"
"Bid high (US$14.2M)" cost 120 -> chance "Award"
"Win" p 0.30
decision "Steelwork package"
"Fixed-price subcontract" cost 150 -> chance "Final account"
"On budget" p 0.80 -> 2,150
"Minor overrun" p rest -> 1,600
"Self-perform" -> chance "Final account"
"On budget" p 0.60 -> 2,150
"Minor overrun" p 0.30 -> 1,300
"Severe overrun" p rest -> -400
"Lose" p rest -> 0
"Bid low (US$12.9M)" cost 120 -> chance "Award"
"Win" p 0.65
decision "Steelwork package"
"Fixed-price subcontract" cost 150 -> chance "Final account"
"On budget" p 0.80 -> 850
"Minor overrun" p rest -> 300
"Self-perform" -> chance "Final account"
"On budget" p 0.60 -> 850
"Minor overrun" p 0.30 -> 0
"Severe overrun" p rest -> -1,700
"Lose" p rest -> 0
"Do not bid" -> 0