The Same Schedule as a Precedence Network
One line — `view network` — and the same document draws the activity-on-node network instead of the bars: a box per task carrying its own early start, duration, early finish, float, and what shortening it actually buys. Both views come from ONE schedule, so they cannot disagree; a network computed by a second pass would be two answers to one question. Reports clean.
Make it your own.
title "Data platform migration"
view network
start 2026-02-02
calendar mon-fri
section "Assess"
task audit "Audit current warehouse" 8d
task model "Target data model" 10d after audit
task pick "Pick the loader" 4d after audit
section "Build"
task land "Landing zone" 6d after pick
task pipe "Build pipelines" 14d after model, land
task qa "Reconciliation tests" 8d after ff:pipe
section "Cut over"
task dry "Dry run" 5d after qa
task cut "Cut over" 3d after dry
milestone done "Legacy off" after cut