Baseline vs Actual — What Was Agreed, Under What Follows

Each bar carries a ghost underneath: the span that was agreed at kick-off. The bar above it is what the current durations and dependencies actually produce. A baseline is the one thing in this engine taken from the document rather than computed, because it is a historical claim and there is nothing to derive it from — everything above it is derived. Reports clean.

Template previewGantt & critical path
ERP rollout — against baseline — Gantt chart with critical path7 tasks; from 2026-01-05 to 2026-04-21, 77 working days; 6 on the critical path; every check ran and found nothing.ERP rollout — against baselineMo 5 Jan 2026 → Tu 21 Apr 2026 · 77 working days · 107 calendar dayscritical path: blue → data → sit → uat → cut → liveshorten first: blue (up to 20d) · uat (up to 15d) · sit (up to 12d)Jan 2026Feb 2026Mar 2026Apr 2026May 202651219262916232916233061320274111825FoundationsProving▲ Blueprint20d · shorten → 20d▲ Data migration build25d · shorten → 7dConfiguration18d · float 7d▲ System integration test12d · shorten → 12d▲ User acceptance15d · shorten → 15d▲ Cutover rehearsal5d · shorten → 5d▲ Go live2026-04-21Go-live window closes 2026-05-29critical — zero floatnear-criticalhas floattotal floatmilestonenon-working daybaselineEvery check ran, and none of them found anything.·Mo 5 Jan 2026 to Tu 21 Apr 2026 — 77 working days across 107 calendar days, on a Mo–Fr week·one critical path, through 6 tasks — shortening any one of them shortens the project, up to the point another path becomes binding·to finish sooner, shorten `blue` by up to 20 working days (the whole task); `uat` by up to 15 working days (the whole task); `sit` by up to 12 working days (the whole task). Anything beyond those figuresmoves nothing — the gain from taking δ days off a task is min(δ, the figure above), and it is zero for every critical task not listed here.✓the deadline of 2026-05-29 (Go-live window closes) is met with 28 working days to spare

Make it your own.

title "ERP rollout — against baseline"
start 2026-01-05
calendar mon-fri
deadline 2026-05-29 "Go-live window closes"

section "Foundations"
  task blue  "Blueprint" 20d baseline 2026-01-05 .. 2026-01-23
  task data  "Data migration build" 25d after blue baseline 2026-01-26 .. 2026-02-20
  task cfg   "Configuration" 18d after blue baseline 2026-01-26 .. 2026-02-13

section "Proving"
  task sit   "System integration test" 12d after data, cfg baseline 2026-02-23 .. 2026-03-06
  task uat   "User acceptance" 15d after sit baseline 2026-03-09 .. 2026-03-27
  task cut   "Cutover rehearsal" 5d after uat baseline 2026-03-30 .. 2026-04-03
  milestone live "Go live" after cut