Baseline vs Actual — What Was Agreed, Under What Follows
Each bar carries a ghost underneath: the span that was agreed at kick-off. The bar above it is what the current durations and dependencies actually produce. A baseline is the one thing in this engine taken from the document rather than computed, because it is a historical claim and there is nothing to derive it from — everything above it is derived. Reports clean.
Make it your own.
title "ERP rollout — against baseline"
start 2026-01-05
calendar mon-fri
deadline 2026-05-29 "Go-live window closes"
section "Foundations"
task blue "Blueprint" 20d baseline 2026-01-05 .. 2026-01-23
task data "Data migration build" 25d after blue baseline 2026-01-26 .. 2026-02-20
task cfg "Configuration" 18d after blue baseline 2026-01-26 .. 2026-02-13
section "Proving"
task sit "System integration test" 12d after data, cfg baseline 2026-02-23 .. 2026-03-06
task uat "User acceptance" 15d after sit baseline 2026-03-09 .. 2026-03-27
task cut "Cutover rehearsal" 5d after uat baseline 2026-03-30 .. 2026-04-03
milestone live "Go live" after cut