Six-Day Site Week — The Calendar Is Not An Assumption
The same durations under a Monday-to-Saturday working week, which is what a construction site runs. The working week is declared, not assumed, so "12 days" means one unambiguous thing and the engine says which — and the non-working days are shaded, so a bar that takes twelve days and spans fourteen is legible as such rather than mysterious. Reports clean.
Make it your own.
title "Roof replacement"
start 2026-04-06
calendar mon-sat
holiday 2026-05-04 "Early May bank holiday"
section "Enabling"
task scaf "Scaffold" 4d
task strip "Strip existing covering" 6d after scaf
task deck "Deck repairs" 5d after strip
section "New roof"
task felt "Underlay and battens" 4d after deck
task tile "Tiling" 12d after felt
task lead "Leadwork" 4d after ss:tile +3d
task rain "Rainwater goods" 3d after tile, lead
section "Off site"
task down "Scaffold down" 2d after rain
milestone done "Practical completion" after down